The shortage of a clear grid capability system within the Czechia undermines the photo voltaic self-consumption enterprise mannequin, and in some elements of the nation, grid bottlenecks delay grid connections.

On April 10, the state-owned Czech Transmission System Operator (ČEPS) was pressured to close down round 400 MW of photo voltaic, or about one-sixth of the nation’s complete PV capability, to make sure stability within the energy system.

“ČEPS determined to activate the prevention plan after exhausting the standard out there operational measures to manage the ability system,” mentioned spokeswoman Hana Klímová.

Usually, the grid operator would ship extra power to neighboring international locations, however that was not attainable on April 10, as all potential importers had a surplus. Czechia is at the moment seeking to broaden its PV fleet on the again of excessive power costs and powerful subsidies.

“The market itself is shifting from residential to business initiatives. We count on C&I to account for 80% of latest initiatives which is a giant change, as a result of within the final three years we now have 50/50 share,” mentioned Radek Orsag, CEO of native distributor SolSol. “We count on between 150 MWp to 200 MWp within the residential section and 600 MWp to 800 MWp within the business.”

The momentum will construct on the fourfold enhance seen in 2022, when a complete of 289 MW shall be put in.

“We count on between 800 MW and 1,100 MW of latest PV capability to be added this 12 months,” mentioned Jan Krcmar, chairman of the Czech Photo voltaic Affiliation (CSA), including that the primary PV initiatives put in in land disappeared after greater than a decade of no exercise on this market section.

Nonetheless, he warned that the Czech grid is just not able to accommodate the rising share of renewables.

“The grid capability drawback is just not a technical (challenge), however a mathematical one,” he mentioned.

In different phrases, the Czechia doesn’t have a clear system the place traders can test if the grid capability is offered in a particular location. In consequence, they generally apply to attach many capacities throughout the nation, to see the place they need to purchase land. Nonetheless, it might freeze the system.

“These reservations for giant PV initiatives are the rationale why some TSOs could refuse to attach many small rooftops although massive installations positioned on the bottom is probably not constructed,” mentioned mentioned Krcmar. “Subsequently, massive self-consumption in some areas is inconceivable and TSOs can power clients to put in smaller methods or prohibit them from injecting any extra into the grid underneath menace in punishment.”

In some elements of the nation, grid bottlenecks translate into delayed community connections. Particularly, on the E.ON-owned community EG.D, clients wait eight to 9 months to attach PV. As rooftop PV rebate funds are tied to connection, many have been ready nearly a 12 months to obtain their cash. This has a knock-on impact on installers, who’re often paid solely after the rebate is settled.

Uneven mode

One other drawback related to the community for photo voltaic in Czechia is the Europe-wide distinctive section metering of its low-voltage grid. This requires most inverter producers to implement firmware modifications to make sure that all photo voltaic consumption goes via one section, enabling a better charge of self-consumption. Not all producers are able to implement such modifications, so a number of Chinese language producers declare the biggest market share.

“The biggest market share within the Czechia in 2022-23 is claimed by GoodWe, Growatt, and Solax. Nonetheless, as a consequence of a restricted provide of asymmetrical inverters and their corresponding batteries, we now have a scarcity available in the market, “mentioned Orsag of SolSol, which reportedly claims greater than 30% of the Czech PV market.

It’s believed that working inverters on this asymmetrical mode interprets into shorter product lifespans of seven to eight years – which finally results in better prices for prosumers.

“The official causes for such a design of the electrical energy market are the soundness of the grid and that it allows individuals to not overload the phases, however the unofficial cause is that the TSOs gather the grid connection prices and costs from that to the tune of a number of million euros a 12 months and naturally there are electrical energy retailers who earn from this,” mentioned Krcmar.

Section metering may also create an enormous imbalance in power communities constructed on the precept of power sharing. For instance, in condominium buildings, because of this one family will get low cost power from photo voltaic in a single section, and one other will get costly power from the grid.

In response to lobbying by the photo voltaic trade, the Czech Senate instructed the Ministry of Trade and Commerce to look into the difficulty of grid design and potential modifications that may very well be applied to beat such limitations.