From pv journal India
CIL Navikarniya Urja has launched bidding for the development of 20 MW grid-connected photo voltaic challenge for captive consumption of Bharat Coking Coal Ltd. (BCCL), one other subsidiary of Coal India. The challenge will likely be constructed at BCCL’s Dugdha Washery facility within the Indian state of Jharkhand.
CIL Navikarniya Urja will act as challenge administration guide for the 20 MW challenge.
The EPC contractor will handle the set up, testing, and commissioning of the challenge, together with the transmission line/cable from the plant take-off level to the interconnecting substations and bays of the substations. It should additionally present operation and upkeep help for the plant and the related transmission system for 5 years.
The whole period of the contract is 2,190 days.
This content material is protected by copyright and will not be reused. If you wish to cooperate with us and wish to reuse a few of our content material, please contact: [email protected].