NTPC Renewable Vitality has began accepting bids to develop as much as 2 GW of pumped hydro power storage initiatives anyplace in India.
Pumped storage initiatives should be commissioned inside 5 years from when they’re awarded. The fee interval consists of 1.5 to 2 years for the detailed preparation of the venture report, land acquisition, research, detailed engineering, and three to three.5 years of development time.
“Early completion of milestones might be acceptable and already established pumped storage initiatives can even be acceptable,” NTPC Renewable Vitality stated within the tender doc.
Every developer should bid a minimal of 200 MW (at one location), going up in increments of 10 MW as much as 2 GW (at a number of areas with a minimal of 200 MW at every location). The minimal storage cycle is six hours in all circumstances.