About 27 GW of photo voltaic and storage tasks stay within the interconnection queue in New York. The grid operator can also be growing 3 GW of wind tasks and a 1.25 GW transmission line.
From pv journal USA
The New York Unbiased System Operator (NYISO) has accomplished closing interconnection research for 27 renewable power and transmission tasks the place builders have agreed on interconnection prices.
The tasks embody 1.6 GW of photo voltaic and 1.5 GW of storage, in comparison with 16 GW of photo voltaic and 14 GW of storage within the NYISO interconnection queue research by the tip of 2021, in accordance with knowledge from Lawrence Berkeley Nationwide Laboratory. The tasks additionally embody 2.3 GW of offshore wind and 0.8 GW of onshore wind, in comparison with 37 GW of offshore wind and 4 GW of onshore wind within the NYISO queue on the finish of 2021.
The permitted transmission venture is a 1.25 GW high-voltage direct present (HVDC) line often called the Champlain Hudson Energy Specific, with development starting in November 2022. The overall value of interconnection for all permitted tasks is about $600 million, together with about $200 million to attach the transmission venture.
The permitted tasks “will assist convey the state nearer to the clear power mandates” of the Local weather Management and Group Safety Act, stated Zach Smith, NYISO vp of techniques and useful resource planning. Beneath that legislation, New York has an interim objective of lowering local weather air pollution 40% by 2030, in comparison with 1990 ranges.
NYISO stated in an announcement that it “continues to work with stakeholders to implement enhancements within the interconnection research course of.” The transmission operator stated that further engineers and venture administration personnel have joined the planning division, and that ongoing focus teams with builders purpose to determine “further areas for of enhancements.”
As well as, new expertise is being developed, NYISO says, that may “create efficiencies within the administration of wants for candidates in addition to NYISO workers.”
Final yr, Texas grid operator ERCOT reported that it had accomplished closing interconnection research for six GW of photo voltaic interconnection requests in 2021, whereas California Unbiased System Operator reported that it had accomplished such research for five GW of photo voltaic. Grid operator Midcontinent Unbiased System Operator within the central United States reported that generator interconnection agreements for six GW of photo voltaic tasks had been filed in 2021. A generator interconnection settlement follows a closing interconnection research.
NYISO has made accessible a listing of 27 tasks in progress. NYISO critiques requests to interconnect the transmission grid utilizing a “cluster research” course of, which NYISO calls a “class yr” course of, described in “The NYISO Interconnection Course of.” In reporting the 27 tasks, NYISO stated the “resolution/settlement course of for the Class Yr 2021” has been accomplished.