Germany’s Federal Community Company (Bundesnetzagentur) has revealed the outcomes of the nation’s sixth tender for rooftop PV initiatives from 300 kW to 750 kW.
It evaluated 342 MW of bids and chosen 191 MW of initiatives within the procurement train. The ultimate costs vary from €0.0880kWh and €0.1080/kWh. The ultimate common worth reached €0.1018.
In its fifth tender, held in March, the company evaluated 213 MW bids and chosen 195 MW initiatives. Remaining costs from €0.0900/kWh and €0.1125/kWh. The final common worth was barely greater at €0.1087.
Within the fourth tender in August 2022, the Bundesnetagentur allotted 201 MW of capability, with last costs from €0.0820/kWh and €0.0891/kWh. The ultimate common worth is €0,084.
The third tender, in Could 2022, reached last costs of €0.07/kWh to €0.0891/kWh.
Within the second PV tender in January 2022, the Bundesnetagentur evaluated 209 bids with a complete capability of 233 MW. It chosen 136 initiatives, with a complete of 154 MW. The ultimate costs vary from €0.0570/kWh and €0.0828/kWh. The ultimate common worth is €0,0743.
Within the first photo voltaic tender in July 2021, the company evaluated 168 bids with a mixed capability of 213 MW. It chosen 114 initiatives, with a complete of 152 MW. The ultimate costs vary from €0.0535/kWh and €0.0789/kWh. The ultimate common worth is €0,0688.